Meet 30-minute Priority 1 alarm response target

On-site response to Priority 1 alarms within 30 minutes at all times; more than two misses per quarter triggers service credits.

ObligationsNordic Property AB · Out-of-hours Security ServicesPast internal dateCriticalSLAVerified
Demo mode (Northstar example, reference date 27 Sept 2026). Buttons here are simulated and nothing is saved. Sign in to work with your own obligations.

Cannot complete: evidence is not sufficient (No evidence uploaded).

Original contract text

Out-of-hours Security Services · §4.2 Emergency response time

The Supplier shall respond on site to Priority 1 alarms within thirty (30) minutes at all times. Failure to meet the response target in more than two (2) instances per quarter entitles the Client to a service credit of SEK 25,000 per additional instance.
Open document view

AI interpretation

AI's own estimate of how well the text supports this reading: 95% — not a guarantee

A measurable SLA with a financial consequence per breach beyond the allowance of two per quarter. Response logs should be reported quarterly.

AI-generated interpretation of contract text. Not legal advice — human review decides the final status.

Automatic quality checks

Source text available Source link checked Interpretation supported Date rule checked Human verified
  • The action claimed by "Meet 30-minute Priority 1 alarm response target" is not established by §4.2. Topic similarity is not source support.
  • 2026-09-21 is an internal planning date, not a contract deadline — it cannot make the obligation overdue under the contract.

Human approval is recorded separately and never makes a field source-verified. Automatic checks compare text and rules only. They do not confirm the interpretation is legally correct — a person must verify it.

  • Requirement: Meet 30-minute Priority 1 alarm response target · insufficient support · §4.2
  • Deadline: 2026-09-21 · insufficient support · §4.2
  • Frequency: quarterly · supported · §4.2
  • Amount: — · not checked · §4.2
  • Consequence: SEK 25,000 service credit per additional missed response. · insufficient support · §4.2
  • Evidence: Quarterly response-time log exported from the alarm system. · insufficient support · §4.2
  • Responsible party: — · not checked · §4.2
  • Trigger: — · not checked · §4.2
  • Conditions: — · not checked · §4.2
  • Exceptions: — · not checked · §4.2
Requirement: not supported by the reviewed sourceDeadline: Internal recommendation / planning · not a contract termFrequency: Stated in contract · source supportsAmount: Stated in contract · source supportsConsequence: Interpreted · partly supportedEvidence: Internal recommendation / planning · not a contract term

Challenging an interpretation is not available yet.

Evidence

Quarterly response-time log exported from the alarm system.

Coverage for this requirement and occurrence: none

No evidence linked.

A document's general approval is not the same as covering this requirement. A reviewer decides.

No evidence linked yet. Upload evidence (sign-in required — demo items can't receive files)

Comments

  • Q3 log still missing. Three responses look above target in the alarm system.

    Anna Lindqvist · 26 Sept 2026

Details

Owner

Mikael Ek

Priority

Critical

Internal planning date

21 Sept 2026Not a contract deadline — cannot make the obligation late under the contract.

Recurrence

Quarterly

Risk

Critical

Financial risk

75 000 SEK

SLA credit

Verification

Verified by Anna Lindqvist

Consequence if missed

SEK 25,000 service credit per additional missed response.

Workflow

  1. Detected
  2. Needs verification
  3. Verified
  4. Assigned
  5. In progress
  6. Evidence uploaded
  7. Evidence review
  8. Completed

Activity history

  1. Comment added — Meet 30-minute Priority 1 alarm response target